SAN JUAN, Puerto Rico — The private operator of Puerto Rico’s power grid confirmed Monday the deferral of $65 million worth of maintenance and improvement projects in the U.S. territory, with some repairs postponed for at least a year because of budget constraints, putting at risk the already troubled grid — and sparking a widespread outcry.

Some of the deferred projects include maintenance of more than 100,000 light posts, fire mitigation and repairs on underground circuits, among other improvements.

Luma Energy’s head of regulatory affairs, Mario Hurtado, told The Associated Press on Monday that the suspended projects, which he aims to bring back next year, risk more outages across the island.

“The risk is always that there will be more failures in terms of public lighting,” Hurtado said.

At a budget hearing on Friday, Hurtado said Luma Energy prioritized other tasks based on “professional judgment,” which they consider calculated risks. The lack of fire mitigation puts the grid at risk as hotter temperatures seize Puerto Rico, increasing the chances of wildfires disrupting power lines.

“We make judgments based on what we have available and what our goals are,” Hurtado said Friday. “Although it entails a risk, it’s an acceptable risk.”

Luma’s budget, proposed to Puerto Rico’s Energy Bureau, includes $1.3 billion for the entire electrical sector, with 65% allocated to Luma, which is in charge of transmission and distribution, 32% to Genera PR, which operates and maintains the grid, and 3% to the Puerto Rico Electric Power Authority.

The budget aims to inject funds into Luma’s customer service, personnel safety and renewable energy projects.

Luma’s announcement to defer millions of dollars’ worth of projects amid chronic power outages has angered many.

“It is unacceptable that Luma Energy can unilaterally decide to suspend crucial tasks,” Jesús Manuel Ortiz, a member of the House of Representatives who’s also running for governor, said in a statement Monday. “It is evident that Luma continues to fail in its responsibilities, and that no one in the Government of Puerto Rico is responsible.”

The company blames a delay in funds disbursement from the Federal Emergency Management Agency. Luma has submitted about 400 projects for approval to upgrade the energy grid, and about 100 have been approved, Hurtado said.

The budget hearing comes as the island of 3.2 million people contends with frequent power outages more than six years after Hurricane Maria ravaged Puerto Rico as a Category 4 storm. The combination of storms, earthquakes and underinvestment has hindered recovery efforts.

A massive blackout in mid-June left over 340,000 customers in the capital, San Juan, and nearby cities without power during a heat wave. Towns in central and southern Puerto Rico are still waiting for Luma to fully restore electricity after a transformer collapsed earlier this month. Over the weekend, Luma shipped a transformer via boat from San Juan to the southern coastal city of Ponce and then transported it to the nearby town of Santa Isabel.

Governor Pedro Pierluisi activated the National Guard to help with the energy crisis and ordered an investigation into the June 13 blackout. The Energy Bureau is also investigating and has directed Luma and Genera PR to submit a plan to stabilize the island’s electrical network.

___

Follow AP’s coverage of Latin America and the Caribbean at https://apnews.com/hub/latin-america



Source link

Lisa Holden
Lisa Holden
Lisa Holden is a news writer for LinkDaddy News. She writes health, sport, tech, and more. Some of her favorite topics include the latest trends in fitness and wellness, the best ways to use technology to improve your life, and the latest developments in medical research.

Recent posts

Related articles

The biggest remaining unsanctioned Russian bank hit with U.S. sanctions, nearly three years into war

WASHINGTON -- Russia's third largest bank, Gazprombank and its six foreign subsidiaries were hit with U.S. sanctions...

Kenya cancels airport and energy deals with Adani group after the U.S. indicts the tycoon

NAIROBI, Kenya -- Kenya’s president said Thursday he has cancelled multimillion-dollar airport expansion and energy deals with...

North Korea and Russia agree to expand their economic cooperation

SEOUL, South Korea -- North Korea and Russia reached a new agreement for expanding economic cooperation following...

Stock market today: Asian shares mostly slip despite Nvidia's solid earnings report

TOKYO -- Asian shares were mostly lower on Thursday after a mixed close on Wall Street, with...

Feds outline 'necessary steps' for Colorado River agreement by 2026 but no recommendation yet

LAS VEGAS -- Federal water officials made public on Wednesday what they called “necessary steps” for seven...

A social media ban for children younger than 16 is introduced in Australia's Parliament

MELBOURNE, Australia -- Australia’s communications minister introduced a world-first law into Parliament on Thursday that would ban...

As US ramps up nuclear power, fuel supplier plans to enrich more uranium domestically

OAK RIDGE, Tenn. -- A supplier of fuel for nuclear power plants announced a $60 million expansion...

How major US stock indexes fared Wednesday, 11/20/2024

U.S. stocks drifted to a mixed finish, though the modest moves for indexes masked some thrashing underneath...